Staybridge Hotel, Brighton
Appointed by Property Construction Northern Ltd, we delivered a new rainscreen cladding installation to the upper levels of the Staybridge Hotel in Brighton.
Project Scope & Objectives
Project 072 involved the installation of new external cladding to Levels 6 and 7 of the Staybridge Hotel in Brighton, working alongside Property Construction Northern Ltd as Main Contractor and Axiom Architects as the appointed design team.
The wall cladding comprised Valcan 3mm VitraDual panels, fully fabricated into cassette format and installed on a Hilti helping-hand support system, with Rockwool Duo Slab insulation throughout.
Outcome & Performance Improvements
The works delivered a high‑performance rainscreen façade with improved fire, acoustic, and thermal performance, providing a durable and modern finish to the upper levels of the hotel.